Date | Activity |
---|---|
May 2008 | Initial assessment survey completed |
May - August 2008 | Consultation in the community carried out |
August 2008 | Applications for funding commenced |
September 2008 | Historical research commenced |
October 2008 | Consultations with English Heritage and South Gloucestershire Council |
October 2008 | Application to the Diocese of Bristol for a faculty (granted) |
October 2008 | First tranche of funding applications complete |
November 2008 | Development of community links and learning and interpretation opportunities commenced |
December 2008 | Design of historical display for the church and website developments commenced |
February 2009 | Full development of learning and interpretation programmes commenced by Marshfield Primary School |
March 2009 | First information leaflet published |
March/April 2009 | Formal Conservation Report completed |
April 2009 | Full project details posted on village website |
July-August 2009 | Second tranche of funding applications |
August 2009 | HLF bid submitted |
September 2009 | Commence detailed planning with Church Recorders |
September 2009 | Project work commences for the pupils of Marshfield School |
September 2009 | Tender process to select Conservators |
October 2009 | Lecture programme developed with the Marshfield and District History Society |
October 2009 | Programme of themed and guided walks to be published |
November 2009 | HLF decision |
November 2009 | Third tranche funding applications |
July 2010 | Conservation work to commence to include on-site training, workshops and an Open Day |
September 2010 | Conservation work complete |