Outline Plan

 

Date Activity
May 2008 Initial assessment survey completed
May - August 2008 Consultation in the community carried out
August 2008 Applications for funding commenced
September 2008 Historical research commenced
October 2008 Consultations with English Heritage and South Gloucestershire Council
October 2008 Application to the Diocese of Bristol for a faculty (granted)
October 2008 First tranche of funding applications complete
November 2008 Development of community links and learning and interpretation opportunities commenced
December 2008 Design of historical display for the church and website developments commenced
February 2009 Full development of learning and interpretation programmes commenced by Marshfield Primary School
March 2009 First information leaflet published
March/April 2009 Formal Conservation Report completed
April 2009 Full project details posted on village website
July-August 2009 Second tranche of funding applications
August 2009 HLF bid submitted
September 2009 Commence detailed planning with Church Recorders
September 2009 Project work commences for the pupils of Marshfield School
September 2009 Tender process to select Conservators
October 2009 Lecture programme developed with the Marshfield and District History Society
October 2009 Programme of themed and guided walks to be published
November 2009 HLF decision
November 2009 Third tranche funding applications
July 2010 Conservation work to commence to include on-site training, workshops and an Open Day
September 2010 Conservation work complete

 